Scenarios Test SAP Clustering Failover

** Team
Activity
Objective
Method
Expected Result
Actual Result
Pass or Not
SAP Clustering Test Scenarios
Stopping HA heartbeat
To simulate heartbeat failure on each node
·         Disable heartbeat on node 1 or node 2
·         Nothing happen. No cluster resource failover. SAP users can work as normal
·         No cluster resource failover. SAP users can work as normal

Starting HA heartbeat
To simulate heartbeat failback on each node
·         Enable heartbeat on node 1 or node 2
·         Nothing happen. No cluster resource failback. SAP users can work as normal
·         No cluster resource failback. SAP users can work as normal

Stopping public network on node 1
To test HA failover on node 2 if node 1's public network is disabled
·         Disable all public network on node 1
·         Node 2 should sense that node1's public is down and should takeover all resources of node 1
·         Cluster resource failover to node 2



Starting public network on node 1
To test HA failback process when node1's public network is enabled
·         Enable all public network on node 1
·         All resource are still activated on node 2 (check node owner)

·         The status of node 1 should be online

·         Failback have to be manually performed
·         Cluster resource still on node 2 ( no failback)

·         node 1’s status  is online

·         Failback done by manual move cluster resource group with MCSG Cluster Admin.

·         Stop SAP CI on Node2 by halt resource

·         Start SAP CI on Node1 by start resource

·         Start SAP DI on Node2

Stopping all public network on node 2
To test HA redundancy interface card on node 2 if node 2's one public network is disabled
·         Disable all public network on node 2
·         Nothing happen. No cluster resource failback. SAP users can work as normal
·         Cluster resource still on node 1

·         Node 2’s status is online

·         Node 2's public interface offline

Starting public network on node 2
To test HA normally  process when node2's public network is enabled
·         Enable all public network on node 2
·         All resource are still activated on node 1 (check node owner)

·         The status of node 2 should be online


·         Cluster resource still on node 1

·         Node 2’s status is online

Power failure on node 1
To test HA failover on node 2 if node 1 suddenly shutdown
·         Turn-off server by pressing the power button located on the server's front panel
·         Node 2 should sense that node 1 is down and should takeover all resources of node 1
·         Cluster resource failover to node 2

Power restore on node 1
To test HA failback process when power is restored and node 1 is properly booted
·         Turn-on server by pressing the power button located on the server's front panel
·         All resource are still activated on node 2 (check node owner)

·         The status of node 1 should be online

·         Failback have to be manually performed
·         No cluster failback to node 1

·         Node 1’s status is online

Power restore on node 2
To test HA failback process when power is restored and node 2 is properly booted
·         Turn-on server by pressing the power button located on the server's front panel
·         All resource are still activated on node 1 (check node owner)

·         The status of node 2 should be online

·         Failback have to be manually performed
·         No Cluster failback to node 2

·         Node 2’s status is online

Scenarios Test case Backup and Restore

** Team
Activity
Objective
Method
Expected Result
Actual Result
Pass or Not
Backup Test Scenarios
DEV System
Backup Testing
To test the backup and procedures from software backup for accuracy and completeness
·         Backup SAP Data
·         Successful - no errors
·         Successful with no error

QAS System
Backup Testing
To test the backup and procedures from software backup for accuracy and completeness
·         Backup SAP Data
·         Successful - no errors
·         Successful with no error

PRDSystem
Backup Testing


To test the backup and procedures from software backup for accuracy and completeness
·         Backup SAP Data From Snap Clone
·         Successful - no errors
·         Successful with no error

Restore Test Scenarios
DEV System
Restore and recovery Testing and startup for usage testing
To test the startup and shutdown procedures for accuracy and completeness
·         Startup and shutdown system, hardware and software services
·         Successful - no errors
·         Successful with no error

QAS System
Restore and recovery Testing and startup for usage testing
To test the startup and shutdown procedures for accuracy and completeness
·         Startup and shutdown system, hardware and software services
·         Successful - no errors
·         Successful with no error

PRD System
Restore and recovery Testing and startup for usage testing
To test the startup and shutdown procedures for accuracy and completeness
·         Startup and shutdown system, hardware and software services
·         Successful - no errors
·         Successful with no error

SAP BASIS Project Activity(Task) Plan for Migrate Physical server to VM

** Myself
No.
Activities
Server /System
Responsible (Name/Team)
Start Date/Time
End Date/Time
Duration
(hh:
mm)
Preparation Step





1
Check Backup to tape complete
PRD
Unix
29-Apr-10 16:45
29-Apr-10 17:00
0:15







Deployment Step





1
Install MS Patch
PRD/PRD
SAP_BASIS
29-Apr-10 17:00
29-Apr-10 17:45
0:45
2
Hold Queue and job - SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 17:45
29-Apr-10 17:50
0:05
3
Stop SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 17:50
29-Apr-10 18:05
0:15
4
Perform P2V Conversion
PRD/PRD
Unix
29-Apr-10 18:05
29-Apr-10 22:05
4:00
5
Configure VM PRD
PRD/PRD
Unix
29-Apr-10 22:05
29-Apr-10 23:05
1:00
6
Shutdown physical servers & Startup SAP Production SAP PRD on VM
PRD/PRD
SAP_BASIS
29-Apr-10 23:05
29-Apr-10 23:25
0:20
7
Check system log (Check Point#1)
PRD/PRD
SAP_BASIS
29-Apr-10 23:25
29-Apr-10 23:40
0:15
8
Release Queue and job -  SAP Production SAP PRD on VM
PRD/PRD
SAP_BASIS
29-Apr-10 23:40
30-Apr-10 00:00
0:20
Backout Plan






Check Point#1





1
Start SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 23:40
29-Apr-10 23:55
0:15
2
Release Queue and job - SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 23:55
30-Apr-10 00:00
0:05







Fallback Plan





1
Start SAP Production SAP PRD
PRD/PRD
SAP_BASIS


0:15
2
Release Queue and job - SAP Production SAP PRD
PRD/PRD
SAP_BASIS


0:05