No.
|
Activities
|
Server /System
|
Responsible (Name/Team)
|
Start Date/Time
|
End Date/Time
|
Duration
(hh:mm) |
Preparation Step
| ||||||
1
|
Check Backup to tape complete
|
PRD
|
Unix
|
29-Apr-10 16:45
|
29-Apr-10 17:00
|
0:15
|
Deployment Step
| ||||||
1
|
Install MS Patch
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 17:00
|
29-Apr-10 17:45
|
0:45
|
2
|
Hold Queue and job - SAP Production SAP PRD
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 17:45
|
29-Apr-10 17:50
|
0:05
|
3
|
Stop SAP Production SAP PRD
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 17:50
|
29-Apr-10 18:05
|
0:15
|
4
|
Perform P2V Conversion
|
PRD/PRD
|
Unix
|
29-Apr-10 18:05
|
29-Apr-10 22:05
|
4:00
|
5
|
Configure VM PRD
|
PRD/PRD
|
Unix
|
29-Apr-10 22:05
|
29-Apr-10 23:05
|
1:00
|
6
|
Shutdown physical servers & Startup SAP Production SAP PRD on VM
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 23:05
|
29-Apr-10 23:25
|
0:20
|
7
|
Check system log (Check Point#1)
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 23:25
|
29-Apr-10 23:40
|
0:15
|
8
|
Release Queue and job - SAP Production SAP PRD on VM
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 23:40
|
30-Apr-10 00:00
|
0:20
|
Backout Plan
| ||||||
Check Point#1
| ||||||
1
|
Start SAP Production SAP PRD
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 23:40
|
29-Apr-10 23:55
|
0:15
|
2
|
Release Queue and job - SAP Production SAP PRD
|
PRD/PRD
|
SAP_BASIS
|
29-Apr-10 23:55
|
30-Apr-10 00:00
|
0:05
|
Fallback Plan
| ||||||
1
|
Start SAP Production SAP PRD
|
PRD/PRD
|
SAP_BASIS
|
0:15
| ||
2
|
Release Queue and job - SAP Production SAP PRD
|
PRD/PRD
|
SAP_BASIS
|
0:05
| ||
Power by < Khronos consulting co., ltd. > |
SAP BASIS Project Activity(Task) Plan for Migrate Physical server to VM