SAP BASIS Project Activity(Task) Plan for Migrate Physical server to VM

** Myself
No.
Activities
Server /System
Responsible (Name/Team)
Start Date/Time
End Date/Time
Duration
(hh:
mm)
Preparation Step





1
Check Backup to tape complete
PRD
Unix
29-Apr-10 16:45
29-Apr-10 17:00
0:15







Deployment Step





1
Install MS Patch
PRD/PRD
SAP_BASIS
29-Apr-10 17:00
29-Apr-10 17:45
0:45
2
Hold Queue and job - SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 17:45
29-Apr-10 17:50
0:05
3
Stop SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 17:50
29-Apr-10 18:05
0:15
4
Perform P2V Conversion
PRD/PRD
Unix
29-Apr-10 18:05
29-Apr-10 22:05
4:00
5
Configure VM PRD
PRD/PRD
Unix
29-Apr-10 22:05
29-Apr-10 23:05
1:00
6
Shutdown physical servers & Startup SAP Production SAP PRD on VM
PRD/PRD
SAP_BASIS
29-Apr-10 23:05
29-Apr-10 23:25
0:20
7
Check system log (Check Point#1)
PRD/PRD
SAP_BASIS
29-Apr-10 23:25
29-Apr-10 23:40
0:15
8
Release Queue and job -  SAP Production SAP PRD on VM
PRD/PRD
SAP_BASIS
29-Apr-10 23:40
30-Apr-10 00:00
0:20
Backout Plan






Check Point#1





1
Start SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 23:40
29-Apr-10 23:55
0:15
2
Release Queue and job - SAP Production SAP PRD
PRD/PRD
SAP_BASIS
29-Apr-10 23:55
30-Apr-10 00:00
0:05







Fallback Plan





1
Start SAP Production SAP PRD
PRD/PRD
SAP_BASIS


0:15
2
Release Queue and job - SAP Production SAP PRD
PRD/PRD
SAP_BASIS


0:05