First step: Site Preparation (Site Prep abreviate) Check server room and overall environment ,Air condition,Power,Floor,Strength ZBefore/After Kickoff)
Next phase :Hardware Implementation
| Site preparation | ||
| Power cord | ||
| Rack entrance | ||
| Rack position | ||
| Site prepare | ||
| Hardware Implementation | ||
| Hardware Delivery | ||
| Hardware Installation and setup | ||
| Install hardware into RACK | ||
| Install Servers | ||
| Install SAN switch 4/8 (2units) | ||
| Install Storage | ||
| Install tape library | ||
| Wiring Cable | ||
| Install Operating System | ||
| Install UNIX and Windows OS | ||
| Mirror OS disks(for Unix) | ||
| Install Tool for Manage (SAN,Backup) | ||
| Configure SAN switch | ||
| Configure Storage | ||
| Assign Disk to hosts | ||
| UAT HW | ||
| Test redundancy (Power cord,Mirror OS,SAN,Lan,Network etc | ||
| Software Implementation | ||
| [Category application] | ||
| Documentation Arrangeing | ||
| System manual | ||
| Disaster recovery actions manual |